We are just beginning works at our new Camden site, and construction is soon to be underway.
If you are a local resident to the area, please have a read of our letter of residence for updates on the project and to find out what is going on in your local Camden area.
Site Monthly Updates
December
Works are scheduled to commence on site for the Harrington Square development. Initial mobilisation will begin, including site setup, hoarding installation, and preparation for groundworks. The project team is finalising logistics and ensuring all compliance measures are in place.
January
Site setup is now complete, and early-stage works are underway. This includes preliminary excavation and preparation for foundation works. Coordination continues with Camden Council to ensure all works align with conservation area requirements.
February
Foundation works are progressing steadily. Piling activities are ongoing, forming a key structural base for the development. The team continues to manage site logistics carefully due to the constrained urban location.
March
Piled foundations are nearing completion. Substructure works are beginning, including groundwork preparation. Activity on site is increasing as the project transitions into the next construction phase.
April
Piling works have now been completed, and substructure groundworks are in full progress. These works will continue throughout April, aiming to complete the ground floor slab by early to mid-May.
A tower crane installation is scheduled for the end of April, requiring a mobile crane for one day. A scaffold gantry will also be installed at the site frontage to ensure pedestrian safety.